Friedman v. Public Utilities Comm’n

by
Ed Friedman and others (collectively, Friedman) appealed the Maine Public Utilities Commission's dismissal of their complaint against Central Maine Power Company (CMP) regarding CMP's use of smart-meter technology. Friedman also appealed the Commission's dismissal of those portions of the complaint that were directed at the Commission and raised constitutional concerns regarding orders previously issued by the Commission. Friedman asserted, among other issues, that the Commission erred because its dismissal of his complaint ignored the Commission's statutory mandate to ensure the delivery of safe and reasonable utility services. The Commission and CMP contended that the complaint was properly dismissed in all respects. Because the Supreme Court agreed with Friedman that the Commission should not have dismissed the portion of the complaint against CMP addressing health and safety issues, the Court vacated that portion of the judgment and otherwise affirmed. View "Friedman v. Public Utilities Comm'n" on Justia Law